Effective November 23, 2026
EV Manufacturing TransitionEngineering notice
VW ID. Polo backlog nears a year as Martorell ramps to 1,200 cars a day
Base ID. Polo trims carry 21-month delivery times as 53,000 orders collide with Martorell's ramp toward 1,200 cars a day in 2027. Battery cells remain the bottleneck.
Scope of change
- Roughly 53,000 ID. Polo orders by end of September; base Trend trim waits up to 21 months in Germany
- Martorell builds up to 1,000 electric cars daily, rising to 1,200 per day (~300,000 a year) in H1 2027
- October cell shortage halted the Martorell line, costing an estimated 1,900 vehicles
- Electric Urban Car Family logged about 150,000 orders by end of September across four models
- PowerCo's Sagunto gigafactory targets stable series production in H1 2027

Around 53,000 orders had been placed for the VW ID. Polo by the end of September, and buyers of the base Trend trim now face delivery times of up to 21 months in Germany. The electric compact car, which starts at €24,995, has become an unexpected success for Volkswagen — and a production problem the group cannot solve quickly.
VW brand chief Thomas Schäfer disclosed the order figure at the Paris Motor Show in October. Dealers have since reported waiting times of more than a year to Automobilwoche, up from the ten months cited in September. Delivery times vary sharply by trim, according to Spanish outlet Motor.es: the Sportline may arrive in five months and the GTI in seven, while the cheapest Trend variant carries the longest queue.
Why cannot VW simply build more?
The ID. Polo is assembled at the Martorell plant in Spain, where it shares a line with the Cupra Raval. A VW spokesperson said the plant currently produces up to 1,000 electric cars per day. Production is set to expand gradually to three shifts in the first half of 2027, reaching full capacity of up to 1,200 vehicles per day — roughly 300,000 units annually.
The spokesperson told Automobilwoche: "Production capacities and the ramp-up of new models are planned long-term and cannot be adjusted short-term to the same extent as this dynamically increasing demand." Demand has developed "significantly more dynamically than originally expected."
Seat-Cupra CEO Markus Haupt told Spanish media in October that the ramp-up would take time. The plan calls for an initial expansion to two and a half shifts and roughly 930 vehicles per day. Moving to three shifts requires secured supplier logistics alongside workforce planning; Seat has hired nearly 1,000 additional employees for the effort.
What is straining the supply chain?
Battery cells are the bottleneck. A cell shortage forced Seat to halt production temporarily on the Martorell electric line in October. Union representatives estimate the multi-day shutdown cost around 1,900 unbuilt vehicles. Spanish media reported further interruptions in the following weeks, plus problems transporting cells from China.
Martorell does operate a high-performance battery assembly facility capable of up to 1,200 battery systems per day, but the cells themselves come from external suppliers such as Gotion. Relief from VW's own battery subsidiary is not imminent: PowerCo's gigafactory in Sagunto, Spain, was scheduled to begin pre-series production in autumn, with stable series production planned for the first half of 2027.
How far does the backlog reach?
The Cupra Raval has drawn more than 52,000 orders, bringing the two Martorell-built models past 100,000 combined. Across the full Electric Urban Car Family — VW ID. Polo, Cupra Raval, VW ID. Cross and Škoda Epiq — Volkswagen had recorded roughly 150,000 orders by the end of September.
The ID. Cross and Škoda Epiq are built in Pamplona, sharing a line with the combustion-engined T-Cross and Taigo. Volkswagen plans total production of 360,000 vehicles there in 2027. The Epiq shows the same demand pattern: Spanish media report more than 80,000 orders and German waiting times of up to 17 months.
What are VW's options and risks?
Volkswagen must now weigh how fast to expand capacity and which models take priority. In Martorell, raising ID. Polo output within current utilisation would come directly at the expense of the Cupra Raval. Additional lines would demand significant investment and several months of lead time, and short-term follow-up orders with suppliers could inflate procurement costs. The success of the compact electric family therefore tests production, supply chains and profitability at once.
The pattern extends beyond Volkswagen. The German Association of Automobile Dealers (VAD) states that more than 40 per cent of new car orders currently involve electric vehicles, with delivery times of three to six months depending on the manufacturer — in some cases more than a year. VAD president Burkhard Weller said: "Our customers sometimes have to wait extremely long for their electric cars and are rightfully frustrated." The VAD argues that electric cars' recent 37 per cent registration share in Germany reflects the trend only with a delay, because many orders will not be delivered and registered until next year.
What to watch next: whether Martorell reaches its two-and-a-half-shift stage near 930 daily units, and whether PowerCo's Sagunto plant hits stable series production in the first half of 2027 as planned.
via electrive.net (Original)
More from Sophie Lindqvist
Show full bio
Correspondent covering money, funding and market shifts around Automotive manufacturing and vehicle production at Autoplant Brief.
336 articles
Also circulated
- VW weighs SSP platform for Martorell, ties decision to wage cuts
- VW to Dismantle 4,100 Cars a Year at Zwickau EV Plant
- VW bets on new SUVs as China wholesale sales slide 27% in September
- SEAT-Cupra Operating Profit Falls to €1M as VW Weighs 2030 Funding
- SAIC Motor Commits $232 Million to New Auto Plant in Spain