ECO-3236 · REV K · effective October 19, 2026
Vehicle Plants & ProductionAPPROVEDEngineering notice
Twelve Modular Cooling Towers Installed in Four Days at 420,000-Unit Plant
A 420,000-unit-per-year Midwest auto plant swapped six field-erected cooling towers for 12 BAC modular units in four days, versus 60-plus days for site-built assembly.
Scope of change
- 12 modular cooling towers installed in four days at a plant with 420,000 vehicles annual capacity
- BAC says a comparable field-erected system would have needed more than 60 days to assemble
- Demolition started no earlier than December; full commissioning deadline was April
- ElitAire engineer Hassan Alhashim: each module installed in about 3 hours
- Factory acceptance testing completed off-site before delivery, cutting on-site construction work

A Midwest automotive plant that builds 420,000 vehicles a year replaced its entire cooling tower bank in four days, using 12 factory-built modular units instead of a field-erected system that would have taken more than 60 days to assemble on site.
The unnamed OEM undertook the swap as part of a broader modernization program covering retooling, new equipment and advanced manufacturing tech. The constraint was timing, not budget theater: demolition couldn't start until December, and site prep, installation and commissioning all had to finish by April. That's a four-month window in a plant that can't politely stop building cars.
The OEM worked with ElitAire LLC, a Michigan-based mechanical contractor, and weighed two paths: replace the six aging field-erected towers with more of the same, or go modular with units built off-site by Baltimore Aircoil Co. A second decision ran in parallel — stick with gear-driven fans or move to direct-drive.
The company chose 12 BAC Series 3000 modular towers fitted with ENDURADRIVE direct-drive fan systems, set on the plant's existing concrete cold-water basin. Reusing the basin mattered; it kept civil work to a minimum at an operating facility.
How fast is four days, really?
Per BAC's figures, each module went in over roughly three hours. Twelve modules, four days. The comparable field-erected route: more than 60 days of on-site assembly, according to the manufacturer.
Hassan Alhashim, lead project engineer at ElitAire, put it plainly: "Instead of taking 2-3 months to erect site-built towers, the modules were each installed in about 3 hours, and the entire process from demolition to completion was accomplished well within the four-month window."
For context: the modular approach compressed what's normally a quarter-year construction job into about 3% of that time — for the installation phase alone. Demolition and commissioning still occupied the rest of the window.
Why off-site builds change the risk picture
Building the modules off-site let the OEM complete visual inspections and factory acceptance testing before the equipment ever reached the plant. That matters in two ways:
- Faults surface at the factory, not on a live production site with a shutdown clock running
- Construction labor and crane time at the operating facility drop sharply, shrinking the downtime exposure
The takeaway is simple: the schedule risk moved from an unpredictable job site to a controlled factory floor.
What to watch next
BAC's 60-day figure for field-erected assembly is the manufacturer's own claim, and plant-specific variables — basin condition, crane access, weather — will move it in either direction. Treat it as directional, not gospel. Direct-drive fans also carry a maintenance story: fewer moving parts than gear drives, which typically means fewer lubrication and alignment jobs over the fleet's life. Watch for follow-on installations at other high-volume plants, and for the OEM — still unnamed — to confirm whether the December-to-April window held without production loss.
Four days for twelve towers. The concrete basin stayed; the schedule risk didn't.
via bnpmedia.com (Original)
More from Daniel Okafor
Show full bio
Senior reporter covering regulation, policy and their impact on Automotive manufacturing and vehicle production at Autoplant Brief.
252 articles