Vehicle Plants & ProductionEngineering notice

TSL exits Agratas Bridgwater cell plant as launch slips to 2028

Agratas says its Somerset cell plant remains on track, but TSL's exit leaves the 40 GWh, £5.2bn Bridgwater project without a named main contractor before a January 2028 start.

Scope of change

  1. Agratas now targets January 2028 for production at its 40 GWh Bridgwater, Somerset cell plant, two years later than the original 2026 plan
  2. The project carries £5.2 billion of total investment, about 4,000 jobs and a £380 million UK government pledge
  3. TSL will leave the site within two to three months, with NG Bailey considered as construction management successor
  4. Jaguar Land Rover has secured interim battery supplies, and its first vehicles will not use UK-made cells
  5. Agratas dismissed Sir Robert McAlpine in June and handed construction management to TSL
Tata Group’s British battery cell factory faces delays
Fig.Tata Group’s British battery cell factory faces delays — Quanlecntt2004 / pixabay

Agratas has moved the start of production at a 40 GWh battery cell plant near Bridgwater, Somerset, to January 2028, two years later than the original 2026 target. The project carries about 4,000 jobs and £5.2 billion of investment, and it now faces the departure of its main contractor.

The factory sits at the Gravity Smart Campus, a development site in Somerset, and Tata Group's battery subsidiary announced it in February 2024. The British government has pledged £380 million. Cells from Bridgwater are meant mainly for Jaguar Land Rover (JLR), the automotive subsidiary Tata owns, which makes Agratas the tier-one cell supplier (a supplier of cells to an automaker) for the group's own vehicles.

What happened to the main contractor?

Three unnamed sources told The Guardian that TSL, the construction specialist Agratas commissioned, has decided to step down as main contractor. TSL took on the job only in June, after Agratas dismissed Sir Robert McAlpine (SRM) and transferred construction management to it. Sources attribute the split to disagreements over the project timeline and costs.

TSL plans to leave the site within two to three months, and Agratas has named no successor. NG Bailey, the firm responsible for the plant's technical building equipment, is reportedly under consideration to take over construction management.

What does this change for Jaguar Land Rover?

For JLR, little changes in the near term. The automaker has secured interim battery supplies from other providers, and The Guardian reports that its plans to increase sales of new electric Land Rover and Jaguar models are not at risk. The harder truth is narrower: the first vehicles will not carry cells built in the UK.

That leaves the Somerset line without a near-term customer inside the Tata group and pushes the supply question for UK-made cells to 2028. Agratas has also flagged batteries for two-wheelers, commercial vehicles and commercial-scale stationary energy storage (grid-scale battery storage), so other customers may carry more weight. Whether recently acquired Iveco has a role there remains unknown.

Some construction has moved ahead. The facility's shell is largely complete, and National Grid has begun work on a substation (the site's electricity connection point). Agratas insists the rest is on schedule. A spokesperson for the company told The Guardian: "We are on track to meet our customer requirements. The Somerset site is a large and complex industrialisation project, and all of our supplier partners are supporting us well as we prepare for the facility's launch phase."

That claim still has to meet output data. The plant has built no cells, Agratas has named no contractor to complete the works, and the company's own phrase, launch phase, describes the period before production starts. A 40 GWh annual capacity and 4,000 jobs remain announced intentions rather than operating facts.

What to watch next

  • Whether Agratas appoints NG Bailey or another main contractor, and whether TSL clears the site within two to three months.
  • Whether January 2028 holds once a contractor is in place and National Grid finishes the substation.
  • How quickly the line can ramp toward 40 GWh once production begins, and who buys the cells.
  • Whether the £380 million government pledge releases in step with construction milestones, and whether JLR commits to Somerset cells for models running after 2028.

The project drew comparisons with Britishvolt, which failed in its early stages partly for want of binding orders; its former north-east England site is now being converted into an AI data centre (computing infrastructure replacing the battery operation). British media expect Agratas to press on despite the setbacks, and the plant's shell, public money and 2028 date give it advantages Britishvolt lacked. Three items decide the outcome: the contractor appointment, the capacity ramp and the policy decisions behind the public money.

via theguardian.com (Original)

Filed under

Share this article:

More from Marcus Bennett

Marcus Bennett

Show full bio

News editor covering regulation, policy and their impact on Automotive manufacturing and vehicle production at Autoplant Brief.

355 articles

Also circulated

« Previous articleNext article »