Effective November 24, 2026

EV Manufacturing TransitionEngineering notice

Fortum produces battery-grade materials in Harjavalta recycling pilot

Fortum has produced battery-grade materials from recycled inputs at Harjavalta, Finland, backed by €86.4m from Business Finland and up to €40m from the EU Innovation Fund — with no scaling timeline yet.

Scope of change

  1. Fortum completed a pilot campaign producing battery-grade materials at Harjavalta, Finland.
  2. Business Finland has approved €86.4 million for the site's planned expansion.
  3. CINEA funding agreement covers up to €40 million from the EU Innovation Fund.
  4. EU Battery Regulation mandates minimum recycled-content shares from August 2031.
  5. Safeloop study pegs European battery recycling losses at about €1.90 per kilogram of battery pack.
Fortum tests new battery recycling process
Fig.Fortum tests new battery recycling process — Finnrich / pixabay

€86.4 million in approved Business Finland funding plus up to €40 million from the EU Innovation Fund stand behind Fortum's push to turn recycled battery scrap into battery-grade raw materials — yet the company has named no date for industrial scaling and no buyers for its output.

The Finnish utility's battery recycling arm completed a pilot production campaign at its Harjavalta site, producing battery materials from recovered inputs. Fortum describes the campaign as proof that its new recycling process can deliver high-purity battery raw materials while cutting CO₂ emissions. Customer qualification feedback has been "promising so far," the company says, and it is in discussions with several potential buyers on offtake agreements.

Anssi Airas, Head of Fortum Battery Recycling, framed the result in supply-chain terms: "Our ability to produce these battery-grade materials for our customers marks a major step forward in advancing battery recycling and strengthening regional supply in Europe." A competitive and resilient battery value chain, he argued, needs both additional capacity and technologies with a genuine competitive advantage.

What does the process actually change?

For practitioners, the technical claim centers on chemistry management. The new process circulates essential process chemicals in an internal closed loop (meaning reagents are recovered and reused within the plant rather than purchased and discarded). Fortum says this cuts chemical consumption, waste generation and CO₂ emissions. The company also pairs the process with electrification of industrial operations and clean electricity, reducing the need for externally supplied chemicals during material conversion.

The caveats matter for anyone benchmarking this against incumbent hydrometallurgical routes. Fortum's announcement gives no recovery rates, no energy consumption figures and no quantified CO₂ savings. Treat the environmental claims as vendor statements until independent production data appears.

Why the economics are unforgiving right now

The timing is not incidental. European battery recycling currently runs at a structural loss: a study published in August under the EU research project Safeloop puts the calculated loss at roughly €1.90 per kilogram of battery pack. The researchers single out hazardous goods transport, battery pack disassembly, and uncertainty over material recovery as the main cost drivers. Their modelling suggests process optimisations could trim recycling costs by about 34 per cent — the gap a technology like Fortum's must close to be bankable.

Regulation is tightening the deadline. From August 2031, the EU Battery Regulation mandates minimum shares of recycled content in certain battery types, creating guaranteed demand for exactly the materials Fortum says it can now produce at grade.

Policy backing and what to watch

The Harjavalta project already carries strategic weight. The European Commission classified it as a strategic project in 2025 under the Critical Raw Materials Act (CRMA). Business Finland, the Finnish economic development agency, has approved €86.4 million for the site's planned expansion. Fortum Battery Recycling has also signed a funding agreement with the European Executive Agency for Climate, Infrastructure and Environment (CINEA) covering up to €40 million from the EU Innovation Fund.

Fortum did not name its prospective offtake partners, and it did not commit to a timeline for scaling the process beyond the pilot campaign. Both gaps are the metrics to track next: a signed offtake agreement would signal buyer confidence in the qualification results, and a dated expansion decision at Harjavalta would convert announced intentions into confirmed capacity. The August 2031 recycled-content mandate remains the regulatory clock every European recycler is working against.

via electrive.net (Original)

Filed under

Share this article:

More from Marcus Bennett

Marcus Bennett

Show full bio

News editor covering regulation, policy and their impact on Automotive manufacturing and vehicle production at Autoplant Brief.

340 articles

Also circulated

« Previous articleNext article »