Effective November 23, 2026
Production TechnologyEngineering notice
Wiremold Lean Turnaround: 3x to 18x Inventory Turns in Nine Years
Art Byrne says batch producers carry 5-6x too much inventory. At Wiremold, value streams and 90% setup cuts took turns from 3x to 18x — and paid back 21 acquisitions in three years each.
Scope of change
- Wiremold went from 3x to 18x inventory turns in nine-plus years under Art Byrne, targeting 20x
- Setup-reduction kaizens cut equipment setup times by an average of 90% with almost no capital spending
- 21 acquisitions at roughly 3x turns recovered their full purchase price in cash within three years each
- Batch producers typically carry 5-6x too much inventory, 45-50% excess space and 25-40% excess headcount
- Steel coil inventory fell from four-plus months to about two days with daily ordering — and no stock-outs

Wiremold went from 3x inventory turns to 18x in just over nine years, and Art Byrne, the retired CEO who led the effort, says the mechanism behind that result applies to any batch manufacturer. In an IndustryWeek commentary, Byrne argues that companies running functional layouts and long setups carry structural levels of waste — and that excess inventory is the cause, not the cure.
The numbers he cites are blunt. Batch producers with functional structures and long setup times, in his experience, consistently show the following profile:
- 25-40% too many people
- 45-50% too much space
- 5x to 6x too much inventory
- Long lead times
- Poor customer service
- Recurring quality problems that resist solution
Why inventory drives the other problems
Most chief executives, Byrne writes, treat inventory as a balance-sheet line item whose only real cost is the interest expense of carrying it. Sales and marketing teams reinforce this view, demanding more stock every time a customer-service issue appears. The result is a buffer that managers believe protects service but that actually generates cost.
The mechanism is straightforward. Excess inventory requires extra space to store and extra labor to move. Producing in batches creates long lead times and poor customer service. Those long lead times then make quality problems hard to trace, because the defect may have occurred four to six weeks earlier. Excess stock also creates safety hazards and obsolescence: Byrne gives the example of a forecast that called for a batch of 300,000 units against actual demand of 10,000 per year.
What happened when Wiremold simply removed inventory
Before Byrne became CEO, Wiremold leadership tried to attack waste by pulling inventory out of the system directly. Turns rose from 3x to 3.6x — and the company nearly went bankrupt from the disruption. The lesson, Byrne writes, is that inventory hides waste; removing it without changing the process exposes problems faster than an unprepared organization can solve them.
The correct sequence, he argues, is to move from batch production to lean first. The batch company operates on "sell one, make 10,000." The lean company operates on "sell one, make one."
Value streams and 90% setup Reduction
The first structural step at Wiremold was replacing the functional organization — all punch presses together, all drill presses together — with value-stream teams built around product families. Each team had a leader and a buyer planner, sat on the shop floor, and controlled every piece of equipment needed to make its product complete and boxed. That layout enabled one-piece flow lines (production moved one unit at a time across unlike machines) that cut lead times from four to six weeks to minutes.
Setup times had to fall to make flow viable. Wiremold ran repeated setup-reduction kaizens — week-long rapid improvement workshops — and cut setup times on varied equipment by an average of 90%, with almost no capital spending.
The 20x target and the acquisition engine
When Byrne arrived, Wiremold turned inventory 3x. He set a target of 20x, a number he chose deliberately. A goal of 5x, he writes, would have let people keep doing the same work slightly better. Twenty times demanded a new operating logic. He described inventory as "the root of all evil" because it hid the waste lean was meant to remove.
The company reached 18x and was on pace for 20x when it was sold. Over the same nine-plus-year period, Wiremold acquired 21 smaller companies that fit its product lines and distribution. Almost every acquisition turned inventory at about 3x, which Byrne called "sleeping money."
The recovery pattern was consistent and paid for the deals in cash within three years:
- Inventory turns of 6x by the end of year one, 8x by year two, 10x or better by year three — roughly one-third of the acquisition cost recovered
- Productivity gains from the same improvement work — another third
- Shorter lead times and better customer service driving sales gains — the final third
After three years, each acquisition contributed growth and cash flow to finance the next one.
Supply chain response at 20x turns
Byrne addresses the standard objection — that customer service suffers at 3x turns and must collapse at 20x. At 3x, a company produces in batches covering two to four months of demand, tying up capacity in products it might sell later rather than items ordered now. Customers, he notes, reliably order exactly what is out of stock and carries a four- to six-week lead time.
At 20x, with one-piece flow and short setups, the plant builds only against actual orders. Wiremold's own case: four-plus months of steel coil inventory from a supplier 300 miles away became daily ordering of more than six trucks per day, about two days of stock, and no stock-outs.
Byrne's closing prescription is two metrics: on-time delivery at a 100% target and inventory turns at an initial target of 20x. Rising turns, he argues, force lead time down and pull productivity, quality, safety and service up with them. During his tenure, the lean program produced a 2,500% increase in Wiremold's enterprise value in just over nine years.
What to watch: whether manufacturers still treating carrying cost as interest expense restructure toward value streams — and whether the 3x-to-10x-in-three-years acquisition playbook survives current tariff and supply-chain volatility.
via amazon.com (Original)
More from Sophie Lindqvist
Show full bio
Correspondent covering money, funding and market shifts around Automotive manufacturing and vehicle production at Autoplant Brief.
336 articles
Also circulated
- Fed paper maps the chip shortage's two-year impact on vehicle output
- Tariffs, AI and Automation Are Redrawing Global Manufacturing Strategy
- CommercialSearch Report: EV Production Growth Loses Steam